netWorkDays(start, end) counts the days from Monday to Friday between two dates. It includes both the
start and the end date, which is right for “how many working days does this period cover” and one too
many for “how many working days did shipping take”.
Copy and paste
Working days in the period, both ends included:
netWorkDays({Order Date}, {Ship Date})
Elapsed working days, as in “shipped in 1 business day”:
netWorkDays({Order Date}, {Ship Date}) - isWorkDay({Order Date})
Working days left in the current month, today included:
netWorkDays(now(), addDateTime(-1, 'DD', addDateTime(1, 'MM', truncDate('MM', now()))))
Is the date a working day? (1 or 0):
isWorkDay({Order Date})
Example
| Order Date | Ship Date | netWorkDays | Elapsed working days |
|---|---|---|---|
| Fri 2026-05-08 | Mon 2026-05-11 | 2 | 1 |
| Sat 2026-05-09 | Mon 2026-05-11 | 1 | 1 |
| Mon 2026-05-11 | Fri 2026-05-15 | 5 | 4 |
| Thu 2026-05-14 | Wed 2026-05-20 | 5 | 4 |
| Fri 2026-05-15 | Fri 2026-05-15 | 1 | 0 |
netWorkDays counts Friday and Monday in the first row, so an order shipped on the next working day
shows 2. isWorkDay returns 1 for a working day and 0 for a weekend, so subtracting it removes the
start day only when it was counted. An order placed on Saturday and shipped on Monday also took one
working day.
What the function assumes
- Weekends are Saturday and Sunday. Other weekend patterns, such as Friday and Saturday, are not supported.
- Both dates are included, and the result is negative when the start is after the end: from Friday 9 September to Friday 2 September 2022 returns −6 in the AWS example.
- Nulls give null. An order not shipped yet has no result. Use
coalesce({Ship Date}, now())to count working days open so far. - Day granularity. The time of day is ignored.
Public holidays
netWorkDays, isWorkDay and addWorkDays know nothing about holidays: Christmas on a Friday counts
as a working day. QuickSight has no holiday calendar setting, so the dependable fix is in the data. Keep
a calendar table in the warehouse with one row per date and an IsWorkingDay flag maintained for your
countries, and compute the working days there, or join the calendar to the dataset. In the analysis,
keep netWorkDays for internal metrics where a holiday or two per month is an acceptable error, and
say so in the visual’s description.